920-220 Exam

Nortel Converged Campus ERS Solution

  • Exam Number/Code : 920-220
  • Exam Name : Nortel Converged Campus ERS Solution
  • Questions and Answers : 64 Q&As
  • Update Time: 2011-10-24
  • Testing Engine (SoftWare Version): $ 50.00
  • PDF (Printable Version) Price: $15.00
  •  

Note: After purchase, we will send questions within 24 hours.

Free 920-220 Demo Download

Examsoon offers free demo for Other Nortel Certification 920-220 exam (Nortel Converged Campus ERS Solution). You can check out the interface, question quality and usability of our practice exams before you decide to buy it. We are the only one site can offer demo for almost all products.

Download 920-220 PDF Demo

Download 920-220 ExamTesting Engine

 

Exam 920-220 Preparation from Examsoon include:

After you purchase our product, we will offer free update in time for 90 days.
100% Pass Guaranteed at First Attempt Or Free Update
Immediate Download After Purchase
Comprehensive questions with complete details
Questions accompanied by exhibits
Verified Answers Researched by Industry Experts
Drag and Drop questions as experienced in the Examsoon
Questions updated on regular basis
our product is in multiple-choice questions (MCQs)


Passing the Nortel 920-220 Exam:Passing the 920-220 exam has never been faster or easier, now with the questions and answers, without the messy 920-220 exam that are frequently incorrect. Examsoon Unlimited Access Exams are not only the cheaper way to pass without resorting to 920-220 tests, but at only $ 50.00 you get access to the exam from every certification vendor.


Our 920-220 practice exams and study questions are composed by current and active Information Technology experts, who use their experience in preparing you for your future in IT.


Nortel 920-220 Search Help Feel free to use search terms below while searching the Net for 920-220 exam:

920-220 brain dump simulations
920-220 Test question
920-220 braindump work
920-220 master exams
920-220 braindump model
920-220 latest test


Commitment to Your Success:

At Examsoon we are committed to you ongoing success. Our exams are constantly being updated and compared to industry standards.


You are not about to purchase a disposable product. 920-220 exam updates are supplied free of charge. Regardless of how soon you decide to take the 920-220 examination certification, you will be able to walk into the testing room as confident as the Certification Administrator.


Skip all the worthless 920-220 tutorials and download 920-220 exam materials with questions and answers and a price too unbelievable to pass up. Act now and download it today!

http://www.Examsoon.com The safer.easier way to get Other Nortel Certification Certification.
 
 
Exam : Nortel 920-220
Title : Nortel Converged Campus ERS Solution


1. A customer is implementing video conferencing devices that require Power-over-Ethernet (PoE). They are planning to use an Ethernet Routing Switch (ERS) 8310 chassis for this deployment. They would also like to install 8600 modules in the chassis. Which statement about this customer scenario is true?
A. Both PoE and 8600 modules are supported in the 8310 chassis.
B. Neither PoE or 8600 modules are supported in the 8310 chassis.
C. The 8310 chassis does not support PoE, but will support 8600 modules.
D. PoE can be supplied via the 8310 chassis, but will not support 8600 modules.
Answer: D

2. Which multicast technology used with the Ethernet Routing Switch allows the router to determine whether any group members exist on its directly-attached networks and switches?
A. IGAP
B. IGMP
C. DVMRP
D. PIM-SM
Answer: B

3. A customer is using an Ethernet Routing Switch (ERS) 8300 to provide Power-over-Ethernet (PoE). They have recently purchased a number of devices that require PoE, and need to increase the PoE capacity on the 8300. They currently have one 8302AC power supply in the 8300 chassis and are not concerned with redundancy. Which procedure is required to provide the most amount of power?
A. Install two additional 8301AC power supplies connected to 220V input.
B. Install one additional 8302 AC power supply connected to 220V input.
C. Install two additional 8302 AC power supplies connected to 220V input.
D. Install three 8301AC power supplies connected to 220V input.
Answer: D

4. A customer is implementing Ethernet Routing Switch (ERS) 5500 series. The deployment scenario requires fiber links that will support 10 Gbps transmission speeds to a Data Center 30 Km away. Which switch and transceivers meet this requirement?
A. ERS 5510 with 10GBASE-ER XFP transceivers
B. ERS 5530 with 10GBASE-SR XFP transceivers
C. ERS 5520 with 10GBASE-SR XFP transceivers
D. ERS 5530 with 10GBASE-ER XFP transceivers
Answer: D

5. The Redundant Power Supply 15 (RPS15) will provide protection against which failure scenario?
A. rolling blackouts
B. power loss to the entire building
C. failure of the primary AC power supply on the switch
D. regional power surges and drops
Answer: C